In March Apex Tile and Marble Ltd. Was contracted by Contour Developments on behalf of 2110 Fitness to install ceramic floor tiles in the front office, entrance, and change rooms (including porcelain tiles in the shower and toilet area).
The initial issues with Apex Tile were the fact that they exploded their original schedule estimate of 4 days for installation which ended up being nearly 21 days. There was a small amount of additional tile work added to the scope of work which was completed on time in 1.5 days, which did not impact the other work. Over the course of the project the schedule delay could never be explained and on several days their workers did not show on the job site. Contour Development did not fulfill their duties as the General Contractor to ensure the work was completed on time with quality.
Throughout the installation period because it was dragged out a number of the tile installers would frequently leave the facility and return with mud and debris (Calgary winters are very muddy due to our constant chinooks) which caused a deep haze across the tiles.
0 comments