We built a house with J. Greg Allen Builders, Inc. ("GAB") We took out a construction loan at the beginning of the process. As work was completed, GAB would take draws against my loan from the bank. The bank would not release a draw without a signed lien waiver from GAB stating that all sub-contractors had been paid up to date. We moved into our house in September.
Towards the end of the project, we began to hear that GAB was paying very slowly. I had a few subs contact me and I worked with GAB to make sure they were paid.
However, now I am learning that even more have not been paid. One sub may try to file a lawsuit against me (and other homeowners).
We paid for this house in full. GAB took all of our loan proceeds but failed to pay the subs. I want GAB to pay the sub-contractors in full.