Independent profile. Not owned, sponsored or endorsed by Southern California Edison.
Southern California Edison Reviews, Complaints & Contacts
Southern California Edison (SCE) is a California investor-owned electric utility regulated by the CPUC and a wholly owned subsidiary of Edison International. Its SEC filings describe Eaton Fire litigation and a compensation program with a November 30, 2026 claim deadline. BBB shows a D- rating with 86 complaints.
Contacts
Customer service & general contact
- Customer service (residential)(800) 284-2365
- Check outage statussce.com/outages-safety/outage-center/check-outa… ↗
- Business customer accounts(800) 990-7788 2 complaints mention this number
- Report an outage(800) 611-1911
- Claims help (non-Eaton Fire)(800) 251-3311
- Claims department (non-Eaton Fire)[email protected]
Show all 12 contacts
Customer service & general contact (continued)
- Eaton Fire program in-person help(888) 912-8528
Billing & payments
- Billing and paymentssce.com/customer-service-center/billing-payments ↗
Account & login
- My Account sign insce.com/mysce/myaccount ↗
Official website
- SCE official websitesce.com ↗
Corporate & press
- SCE jobs and careersedisoncareers.com ↗
Reference numbers (not support lines)
- Listed by BBBBBB-listed number; also a dial link on SCE's own help page(800) 655-4555 3 complaints mention this number
Locations
- Headquarters2244 Walnut Grove Avenue, Rosemead, CA 91770
- Mailing addressP.O. Box 600, Rosemead, CA 91771-0001
- Mailing addressP.O. Box 900, Attn: Claims Department, Rosemead, CA 91770
Company Information
- Legal name
- Southern California Edison Company
- Founded
- 1909
- Business type
- California investor-owned electric utility (SCE), a wholly owned subsidiary of Edison International, regulated by the California Public Utilities Commission
- Website
- sce.comSource: sce.com: SCE About page, checked
- Headquarters
- Rosemead, CASource: Edison International and SCE joint Form 10-Q for the quarter ended June 30, 2026, checked
- Owned by
- Edison InternationalSource: Edison International and SCE joint Form 10-Q for the quarter ended June 30, 2026, checked
SCE is a California investor-owned electric utility: its registrant filings with the SEC list Southern California Edison Company as a California corporation at 2244 Walnut Grove Avenue, Rosemead, a wholly owned subsidiary of Edison International. The CPUC lists it among the electric utilities its Consumer Affairs Branch handles complaints for. BBB shows it as not BBB accredited with a D- rating and 86 complaints in three years; the BBB file records that rating, not a finding about the utility's operations.
The documented record includes a $110 million fine and other measures in a 2021 SED agreement (without admission of imprudence, negligence or liability). The record also includes a 2025 SED citation of approximately $2 million for the Fairview Fire. It also includes an August 4, 2026 Los Angeles County Fire Department report (investigated with CAL FIRE) attributing the Eaton Fire's cause to electrical arcing events on an out-of-service SCE tower. SCE's 10-Q (filed before that report) addresses the matter by saying it believes it is likely its equipment was associated with the ignition. The record also includes an open SED investigation and a Los Angeles County District Attorney's Office review, and large pending wildfire litigation. A customer with a billing or service problem has a defined route: SCE first, then the CPUC Consumer Affairs Branch.
Independent Sources
Complaint Themes
Reviews & Complaints on USAComplaints
19 complaints linked to the Southern California Edison profile are published on this site (2005-2012). None are from 2023-2026.
- Service refused for new apartment because of prior tenants' fraud
- Spam
- Deposit refund sent to state unclaimed property instead of me
- Sister's outstanding balance transferred to my account without notice
- Bill jumped from $130 to over $900 after rate change
Show 14 more complaints on this page
- Returned check fee charged for typo on online payment
- Charged for old apartment service after daughter moved out
- Outrageous $701 bill that Edison admitted was estimated
- Power shut off twice over disputed penalty and reconnection fee
- Electric bill far higher at new home despite minimal usage
- Deposit demanded and power pulled door to door
- Advice on documenting and escalating disputes with the utility
- No power for two months over another person's unpaid bill
- Power cut over $55 balance after paying website balance
- Electric bill jumped to $826.38 while on vacation
- Getting the run around on updating my credit report
- Electric service not turned on for days despite emergency with baby
- Charged for previous roommate's overdue bill
- Account closed without consent after another person requested service
Complaint record: BBB, Trustpilot and this site's archive
BBB. The BBB profile for Southern California Edison Company, Rosemead, CA shows 'NOT BBB Accredited', a BBB rating of D- with the stated reason 'Failure to respond to 5 complaint(s) filed against business'. The profile also shows 86 total complaints in the last 3 years, 59 complaints filed in the last 12 months, and 0 customer reviews. Trustpilot's page for www.sce.com is unclaimed and shows 60 reviews with a 1.5 rating, and says it does not fact-check reviews. These are different platforms measuring different things; a BBB letter grade is BBB's own rating, and the number of complaints should be read against the size of a utility serving millions of customers.
This site's own archive. usacomplaints.com holds 19 approved posts that name Southern California Edison or Edison International: 18 name SCE as the subject (written between 2005 and 2012) and one, from 2001, names Edison International. They are individual accounts, and SCE's responses are not recorded in them. Posts that concern other utilities with similar names (for example SCE&G in South Carolina, Con Edison, Commonwealth Edison) are not counted.
Of those 18 posts, 12 dispute a bill amount or a charge. Another 11 mention power being shut off, not turned on, or an account being closed. Another 4 describe a charge or balance that the writer says belongs to another person or an earlier tenant. Another 3 mention a deposit. A post can fall into more than one group. The archive is a historical record of what individual writers alleged and does not describe current SCE practices.
Had an experience with Southern California Edison? Tell other people what happened.
Submit a ComplaintSouthern California Edison customers: contact, billing disputes, claims and where to complain
Southern California Edison (SCE) delivers electricity to customers in its Southern California service area and is regulated by the California Public Utilities Commission (CPUC). The steps follow SCE's own pages and CPUC pages.
Who to call. SCE's customer support page lists Customer Service at (800) 284-2365, Business Customer Accounts at (800) 990-7788, and (800) 611-1911 to report an outage. Keep the date, time and name or ID of each representative, and your account number. CPUC advises customers to give the utility the first chance to resolve a billing or service problem and to keep a record of each contact.
If the bill looks wrong. CPUC says to contact the utility directly about what you are billed for, bill explanations, payment arrangements and starting or cancelling service. CPUC's FAQ says that if a utility cannot read a meter it estimates usage from the same period of the previous year and corrects the bill when it can read the meter. CPUC's FAQ also says that the customer is told if bills are estimated for more than 3 months in a row. SCE's Billing & Payment page also lists a Budget Billing Plan, which it describes as paying for annual service in 11 equal monthly payments that 'does not reduce the amount of your bill', and payment help under 'Financial Assistance'.
Disconnection and deposits. CPUC's FAQ states that before disconnecting, a utility must give a 15-day written notice stating the reason, the amount to pay and the earliest disconnection date, followed by a second notice at least 48 hours before. The FAQ also states that disconnections may not occur on a weekend or legal holiday unless there is a safety issue. The FAQ adds that for electric and gas utilities a residential deposit cannot be more than two times the average monthly bill. If service is in jeopardy of being disconnected, CPUC's Consumer Affairs Branch asks you to call (800) 649-7570.
If SCE does not resolve it. File an informal complaint with the CPUC Consumer Affairs Branch: online at the CPUC 'Utility Complaint' page, by phone at (800) 649-7570 (Monday to Friday, 8:30 a.m. to 4:30 p.m.), by fax at (415) 703-1158. You can also mail it to 505 Van Ness Avenue, San Francisco, CA 94102-3298. CPUC says its caseworkers 'interact with the utilities to attempt to resolve any problems'. A formal complaint is a separate process CPUC describes on its website.
Damage or loss claims. For property damage, food loss or other losses a customer attributes to SCE, SCE's claims page says claims can be filed online, by email ([email protected]), fax or mail (P.O. Box 900, Rosemead, CA 91770), with help at (800) 251-3311. SCE says its goal is to decide most claims within 30 days, that it is responsible for losses 'due to our negligence' and not for outages from causes outside its control (see its Tariff Rule 14). SCE also says that denied claims may be taken to civil court including small claims, and that the statutes of limitation it lists are 3 years for property damage and 2 years for bodily injury. The CPUC 'does not rule on the merits of individual claims', according to SCE's page.
Eaton Fire claims. SCE directs Eaton Fire claims to a separate Wildfire Recovery Compensation Program (see the regulator and litigation sections); its FAQ states a claim deadline of November 30, 2026.
Regulators and investigations: CPUC, Safety and Enforcement Division and wildfire matters
The facts on this page come from the Edison International and SCE joint Form 10-Q for the quarter ended June 30, 2026 (filed July 30, 2026), which is the company's own SEC disclosure. The facts also come from an August 4, 2026 Los Angeles County press release, and from an SCE Form 8-K. They are descriptions of investigations and regulatory processes as the sources state them.
More on regulatorsShow less
2017/2018 wildfires and mudslides (SED agreement). The 10-Q says that in October 2021 SCE and the CPUC's Safety and Enforcement Division (SED) executed an agreement resolving SED's investigations into the 2017/2018 Wildfire/Mudslide Events and three other 2017 wildfires for aggregate costs of $550 million. The costs were made up of a $110 million fine paid to the State of California General Fund, $65 million of shareholder-funded safety measures. The costs also include SCE waiving its right to seek cost recovery in CPUC-jurisdictional rates for $125 million and $250 million of third-party uninsured claims payments (and related financing costs) in the Thomas/Koenigstein/Montecito and Woolsey litigation. It also states that SCE did not admit imprudence, negligence or liability in that agreement.
Eaton Fire (January 2025): fire-agency report, SCE's statements and open reviews. On August 4, 2026 the Los Angeles County Fire Department (LACoFD) released redacted investigative reports on the cause of the Eaton Fire. The County's press release says the LACoFD Arson Fire Investigation Unit conducted the investigation jointly with CAL FIRE. The release adds that 'the investigation concluded that the cause of the wildfire conflagration was due to the electrical arcing events that took place on the out-of-service Southern California Edison (SCE) tower'. It says the reports are redacted because the Los Angeles County District Attorney's Office 'has an ongoing review of the evidence from this fire'.
This is an investigative conclusion of the fire agencies, not a court judgment, a CPUC finding or a finding of this site. The 10-Q (filed July 30, 2026, before the release) says the SED is conducting an investigation. The filing also says that the District Attorney's Office has an ongoing investigation 'for the purpose of determining whether any criminal violations have occurred', and that SCE 'is not aware of any basis for' felony liability. SCE's own position in that 10-Q is that it 'has not conclusively determined that its equipment caused the ignition'. SCE also says that 'a viable explanation is that a de-energized idle SCE transmission facility in the preliminary area of origin was associated with the ignition'. SCE further says that it 'believes that it is likely that its equipment was associated with the ignition'.
LAist reported on the release that an SCE spokesperson said the company was 'currently reviewing' the report. The 10-Q also says any fines and penalties incurred in connection with the Eaton Fire 'will not be recoverable from insurance, from the Wildfire Fund, or through electric rates'. The CPUC will later review SCE's Eaton Fire costs in a formal proceeding; the 10-Q says no final decision has yet applied the California wildfire cost-recovery prudency framework.
Other SED actions described in the 10-Q. For the 2022 Fairview Fire (Riverside County), the 10-Q says the SED issued a citation in March 2025 for approximately $2 million for alleged violations of SED rules, including failure after the fire to comply with clearance requirements for an electrical conductor. The filing adds that SCE received a November 2023 CAL FIRE report of investigation 'in which CAL FIRE finds that the Fairview Fire was caused when a sagging SCE electrical conductor came in contact with a communication line'.
For the 2022 Coastal Fire (Orange County), it says the SED issued a notice of violation in 2025. The filing adds that SCE received a September 2024 report from the Orange County Fire Authority, 'in which the OCFA finds that the Coastal Fire was unintentionally caused by sparks from overhead SCE electrical equipment igniting vegetation under the equipment'. For the 2019 Saddle Ridge Fire, it says the SED issued a report listing alleged violations of CPUC General Orders and that, as of the filing, an inverse condemnation bench trial had been set for October 2026. These are the agencies' findings as SCE's filing reports them.
Wildfire Fund and rate recovery. The 10-Q says the Wildfire Fund administrator 'has confirmed that the Eaton Fire is a "covered wildfire"' and that SCE 'will be reimbursed for losses incurred in excess of $1.0 billion' for eligible third-party damage claims, subject to the administrator's approval. It also describes the Woolsey Settlement Agreement as 'a settlement agreement entered into between SCE and intervenors in September 2025 in the CPUC-jurisdictional rate recovery proceeding related to the Woolsey Fire'. SCE's Form 8-K says that on July 28, 2026 SCE Recovery Funding issued $1,953,948,000 of Senior Secured Recovery Bonds, Series 2026-A. The 10-Q says the proceeds finance cost recoveries authorized under the Woolsey Settlement Agreement and that the bonds are serviced from non-bypassable rates and other charges collected from certain existing and future customers in SCE's service area.
Wildfire safety oversight. The 10-Q states that in February 2026 the Office of Energy Infrastructure Safety issued a final decision approving SCE's 2026-2028 Wildfire Mitigation Plan. In March 2026 it issued SCE's safety certification, valid until the later of March 2, 2027 and when the Office acts on SCE's next request.
Court and claims record: wildfire litigation and settlements
SCE's joint Form 10-Q for the quarter ended June 30, 2026 reports the following as of July 23, 2026. Lawsuits are allegations until decided, and SCE says it has not admitted wrongdoing or liability in any of the settlements on this page.
More on the lawsuitsShow less
Eaton Fire. SCE reports awareness of approximately 2,000 currently pending unsettled lawsuits representing approximately 32,000 individual plaintiffs, plus subrogation plaintiffs and public entity plaintiffs including the United States of America, the County of Los Angeles, the City of Pasadena and the City of Sierra Madre. Some were filed as purported class actions, and the 10-Q says a bellwether jury trial had been set for January 2027 as of July 23, 2026. In January 2026 SCE filed a cross-complaint against certain public and private entities whose actions or inaction it says may have contributed to the losses.
Through June 30, 2026 SCE reports settlements with insurance claimants and claimants under its Wildfire Recovery Compensation Program, with $517 million of Eaton Fire settlements paid and $1.6 billion in losses recorded for settlements. It says claimants who settle release SCE and Edison International and that no admission was made. On October 1, 2026 SCE issued a news release (its own statement, as of that date) saying the program had received more than 5,000 claims. The release said SCE extended nearly 2,900 offers to almost 7,200 claimants totaling more than $1 billion, and paid more than 3,850 claimants over $535 million. The release also says that on average SCE delivers offers 36 days after receiving a substantially complete claim.
2017/2018 Wildfire/Mudslide Events. SCE reports 9 pending unsettled lawsuits (21 plaintiffs) related to the Thomas and Koenigstein Fires and the Montecito Mudslides and 17 (28 plaintiffs) related to the Woolsey Fire, settlements with approximately 13,800 individual plaintiffs and $9,707 million of settlements paid since inception. In the Woolsey Fire litigation the 10-Q says that, as of July 23, 2026, a damages and liability trial with the California Office of Emergency Services (Cal OES) was set for October 2026 and one opt-in household was set for trial on November 16, 2026. The 10-Q also reports that the court denied class certification in the one purported class action in the Thomas/Koenigstein litigation and that plaintiffs have appealed.
Other wildfire events. SCE reports having settled substantially all claims related to the 2017 Creek Fire, 2020 Bobcat Fire and 2020 Silverado Fire, and describes pending litigation for the 2019 Saddle Ridge, 2022 Coastal and 2022 Fairview fires.
Wildfire Recovery Compensation Program. SCE's program FAQ describes it as voluntary: participation 'does not affect any rights until a claimant accepts the compensation offer and signs a release'; Fast Pay offers are promised within 90 days of a substantially complete claim. An offer 'becomes void' if not accepted within 90 days, after which the claimant retains the right to litigate; and accepting requires a signed, notarized release of claims against SCE and related entities. The program page states that participation 'does not constitute an admission of liability or wrongdoing'.
The same FAQ says that settlement offers 'are not negotiable' (a claimant may add information or request a Detailed Review), that a Detailed Review offer can be expected 'within nine months once all required documentation has been submitted'. The same FAQ also says that signing a full release 'waives all past and future claims related to the Eaton Fire, against SCE and related entities'. The same FAQ also says that upon payment any ongoing litigation 'must be dismissed with prejudice', and that claimants 'are solely responsible for any liens', including those of healthcare providers, mortgage lenders, attorneys, insurers or government agencies. Its closing statement reads that the company 'expressly denies responsibility for the underlying events'. Claimants should read the Protocol and consider independent legal advice before signing.
Court & Public Records
Eaton Fire litigation (approx. 2,000 lawsuits; plaintiffs include individuals, subrogation insurers, the United States, County of Los Angeles, City of Pasadena and City of Sierra Madre) v. Southern California Edison Company and Edison International
FiledAs of July 23, 2026, SCE reports approximately 2,000 pending unsettled lawsuits representing approximately 32,000 individual plaintiffs, plus subrogation and public entity plaintiffs; a bellwether jury trial was set for January 2027. SCE says it has settled with insurance and Wildfire Recovery Compensation Program claimants without admission of wrongdoing, and in January 2026 filed a cross-complaint against certain public and private entities. Allegations are unproven; no judgment is described in the filing.
2017/2018 Wildfire/Mudslide Events litigation (Thomas, Koenigstein, Woolsey fires and Montecito Mudslides) v. Southern California Edison Company
FiledAs of July 23, 2026, SCE reports 9 pending unsettled lawsuits (21 plaintiffs) on the Thomas/Koenigstein Fires and Montecito Mudslides and 17 (28 plaintiffs) on the Woolsey Fire, settlements with approximately 13,800 individual plaintiffs, and $9,707 million of settlements paid since inception, with no admission of wrongdoing or liability. Class certification was denied in the one purported class action and plaintiffs have appealed. In the Woolsey Fire litigation, as of July 23, 2026, a damages and liability trial with Cal OES was set for October 2026 and one opt-in household for trial on November 16, 2026; these dates are as stated in the 10-Q, and trial status after that date is not reported.
CPUC Safety and Enforcement Division agreement resolving investigations of the 2017/2018 Wildfire/Mudslide Events and three other 2017 wildfires
SettledPer SCE's Form 10-Q: in October 2021 SCE and the SED executed an agreement for aggregate costs of $550 million: a $110 million fine to the State of California General Fund, $65 million of shareholder-funded safety measures, and SCE's waiver of cost recovery in CPUC-jurisdictional rates for $125 million and $250 million of third-party uninsured claims payments in the Thomas/Koenigstein/Montecito and Woolsey litigation. The agreement also imposes reporting and safety-study obligations. SCE did not admit imprudence, negligence or liability.
Who SCE is: ownership, service area and what the CPUC regulates
Southern California Edison Company is a California corporation headquartered in Rosemead, California, and a wholly owned subsidiary of Edison International (NYSE: EIX), per the joint Form 10-Q. SCE says it delivers power to 15 million people in 50,000 square miles across central, coastal and Southern California, excluding the City of Los Angeles and some other cities, covering more than 180 incorporated cities and 15 counties (company statement). SCE says it was officially incorporated in 1909.
SCE is an electric delivery utility, so billing disputes and service-quality complaints are within the CPUC Consumer Affairs Branch's scope; the Branch does not handle municipal utility complaints, according to CPUC. Some Southern California customers receive electricity through community choice aggregators or municipal utilities, in which case the generation supplier or city utility, not SCE, is the right first contact for generation charges (SCE's Help Center lists a Community Choice Aggregation topic).
SCE's 10-Q describes the 2025 General Rate Case (GRC) decision, which the CPUC adopted in 2025 and which SCE says increased its authorized revenue starting in the third quarter of 2025 with a 2026 escalation mechanism. Rates and the revenue SCE may collect are set in CPUC proceedings; customers can follow them and comment through the CPUC.
Company Relationships
- Owned byEdison International
Frequently Asked Questions
How do I dispute a Southern California Edison bill?
For Southern California Edison, CPUC says to contact the utility directly first about what you are billed for and bill explanations, and to keep the date, representative's name and details of each call. SCE's customer service line is (800) 284-2365 (business accounts (800) 990-7788). If SCE does not resolve it, you can file an informal complaint with the CPUC Consumer Affairs Branch at (800) 649-7570 or online.
How do I pay my Southern California Edison bill?
SCE's Billing and Payments page has a Make a Payment link that leads to ways to pay your bill. It also describes getting an e-bill through a participating bank's bill pay service and making payments there, and paying by check or money order by mail. Residential customers send it to Southern California Edison, P.O. Box 600, Rosemead, CA 91771-0001, and business customers send it to Southern California Edison, P.O. Box 300, Rosemead, CA 91772-0001. Use the Billing and payments link in Contacts.
How do I check or report a power outage with Southern California Edison?
SCE's Outage Center lets you search for an outage by service address, outage number or meter number, and shows current and scheduled outages. If your outage does not appear in the results, the page has a Report Outage button, and SCE asks you to call (800) 611-1911 if you still do not see an outage.
Where do I log in to my Southern California Edison account?
SCE's website has a Log In button for My Account, which it says you can use to pay your bills, check your usage and more. New users can create an account with the Register link. If you cannot sign in, SCE customer service is (800) 284-2365.
How do I file a CPUC complaint about SCE?
For Southern California Edison, CPUC's Consumer Affairs Branch accepts complaints by phone at (800) 649-7570 (Monday to Friday, 8:30 a.m. to 4:30 p.m.), online, by fax at (415) 703-1158 or by mail to 505 Van Ness Avenue, San Francisco, CA 94102-3298. CPUC recommends first giving the utility a chance to resolve the issue, and says written complaints are evaluated and, if applicable, submitted to the utility as an Informal Complaint.
What notice must SCE give before disconnecting service?
According to CPUC's FAQ, a utility such as Southern California Edison must give a 15-day written notice stating the reason, the amount to pay and the earliest disconnection date, then a second notice at least 48 hours before disconnection. The utility may not disconnect on a weekend or legal holiday unless a safety issue requires it. CPUC advises calling its Consumer Affairs Branch at (800) 649-7570 if service is in jeopardy of being disconnected.
How do I file a claim with SCE for damage or food loss?
SCE's claims page says claims can be submitted online or by email ([email protected]), fax or mail (Attn: Claims Department, P.O. Box 900, Rosemead, CA 91770), with help at (800) 251-3311. SCE says it aims to decide most claims within 30 days, and that it is not responsible for outages or losses from causes outside its control, citing Tariff Rule 14. Denied claims may be taken to civil court, including small claims.
How do I file an Eaton Fire claim with SCE, and what is the deadline?
SCE's Wildfire Recovery Compensation Program FAQ states that claims can be submitted online or in person (call (888) 912-8528) and that the deadline is November 30, 2026. The program is voluntary, and claimants keep their legal rights until they accept an offer and sign a release. Accepting requires giving up claims against SCE related to the Eaton Fire. SCE says the program is not an admission of liability.
What has been found about the cause of the Eaton Fire and SCE's role?
On August 4, 2026 the Los Angeles County Fire Department released redacted investigative reports on the Eaton Fire and the Southern California Edison tower. The department said its investigation with CAL FIRE 'concluded that the cause of the wildfire conflagration was due to the electrical arcing events that took place on the out-of-service Southern California Edison (SCE) tower'. The County says the District Attorney's Office has an ongoing review of the evidence. That is a fire-agency investigative conclusion, not a court judgment or a CPUC finding. SCE's Form 10-Q (filed July 30, 2026, before the release) says SCE 'has not conclusively determined' that its equipment caused the ignition but that it believes it is 'likely that its equipment was associated with the ignition'. LAist reported that an SCE spokesperson said the company was reviewing the report. Lawsuits and the SED and District Attorney reviews are ongoing.
Who owns Southern California Edison?
The joint Form 10-Q of Edison International and SCE describes SCE as a wholly owned subsidiary of Edison International, which is listed on the NYSE under EIX. SCE's own About page says the same. SCE's customers are the electricity users in its service area, and its rates are set by the CPUC.
Is SCE BBB accredited and what is its BBB rating?
Southern California Edison is not BBB accredited. BBB's Rosemead listing for Southern California Edison Company showed a D- grade on October 11, 2026, citing 'Failure to respond to 5 complaint(s) filed against business', with 86 complaints over three years (59 in the latest 12 months) and no customer reviews. Three other SCE listings on BBB carry the same grade.
What if my electricity generation comes from a community choice aggregator and not SCE?
SCE's customer help center lists a Community Choice Aggregation topic, and CPUC states that its Consumer Affairs Branch does not handle municipal utility complaints. For generation charges from a community choice aggregator or a city utility, the first contact is that provider; SCE still delivers the power and handles the meter and outages.
Related Complaints
Role in the other company’s page
Sources (10)
Southern California Edison (own site)
Public records
- CPUC Utility Complaint page: the Consumer Affairs Branch 'assists consumers with resolving disputes involvi… cpuc.ca.gov
- Edison International and SCE joint Form 10-Q for the quarter ended June 30, 2026 sec.gov
- Los Angeles County press release 'County of Los Angeles Fire Department releases the investigative reports… lacounty.gov
- CPUC Consumer Affairs Branch page: 1-800-649-7570, Monday-Friday 8:30 a.m.-4:30 p.m. cpuc.ca.gov
- SCE Form 8-K sec.gov
Review sites
Other
- Wildfire Recovery Compensation Program FAQ: 'The deadline to submit a claim is Nov. 30, 2026' energized.edison.com
- LAist article on the Eaton Fire cause report: an SCE spokesperson said the company is 'currently reviewing'… laist.com
- SCE newsroom.edison.com